PROCUREMENT POLICY
1. PROCUREMENT OF GOODS
PURPOSE OF PROCUREMENT
The overall purpose of procurement regulations is to ensure that Al Karrar Engineering Co gets the
highest quality of desired goods and services at the best price possible. Further, the regulations are
aimed at streamlining the process of procurement while maintaining adequate controls. These
procurement procedures apply to all staff involved in the procurement process and to all types of
procurement.
THE PROCUREMENT COMMITTEE
The Al Karrar Engineering Co procurement committee shall meet when there is a need to deliberate
on issues pertaining to procurement.
The key terms of reference for the committee shall be to:
i) Award tenders
ii) Approve orders
iii) Award contracts
iv) Approve variation of contracts conditions
SEPARATION OF DUTIES
There shall be the proper separation of duties between:
i) The person who orders a particular purchase from a vendor.
ii) The person who satisfies that the goods supplied are satisfactory.
iii) The person who accepts goods into the store.
iv) The person who authorizes payment.
PROCUREMENT PLANNING
Procurement planning is part of the annual budgeting process. Each departmental head is responsible
for planning his/her project’s estimated procurement needs on an annual basis through the use of the
annual procurement plan (APP), which indicates the items to be bought in the various quarters of the
year. The procurement officer will use the APP to plan for requisitions. It is crucial that the
procurement
committee discuss the APP at the beginning of each year and as needs may arise within the year. The
APP will also require the final approval of the project coordinator, who will share it with the
executive
director for comments before approval.
PROCUREMENT REQUISITION (PR)
Each specific procurement procedure process shall be initiated by procurement requisitions to the
procurement officer from the requesting department and should show detailed specifications and
requirements for the item(s) being requested. They should also indicate that the item is budgeted for.
The PRs allow the departments flexibility within the overall annual plans regarding specifications,
exact
quantities, delivery dates, etc. They are also used to cater for unplanned or emergency
procurement.
The PR form will show the following:
i) Items required.
ii) Quantities.
iii) Delivery dates and locations.
iv) Accounting information.
v) Whether procurement is within APP/budget or emergency or unplanned.
vi) Signature of the preparing person.
vii) The departmental head.
Some donors do prescribe some conditions or restrictions required to be observed in the course of
procurement pertaining to the project they fund. It is the responsibility of the procurement committee
to ensure that such donor requirements and restrictions are observed in the procurement of goods and
services but within the framework of Al Karrar Engineering Co procurement guidelines.
All requisitions must be signed by the departmental heads or designate, who should ensure that the
item(s) are in APP or should seek authority to procure as per policy. Any persons designated to
authorize requisitions in an acting capacity must have the authority given in writing clearly stating
the
period authorized.
CONTROLS ON PROCUREMENT
Goods and services will only be procured within approved budgets except in case of emergencies,
which has to be approved by the executive director. Thus, in addition to being responsible for
preparing
the APP/budget, the departmental heads should ensure that actual procurement throughout the year
remains within the budget. Each requisition should reference the APP line bearing the item or
requisition and if needed, be attached to the page of the APP where the such line is
contained.
The financial officer shall assist the procurement officer in conducting periodic checks on
procurement
activities to ensure that they conform to APPs, donor procurement requirements, and Al Karrar
Engineering Co policies and procedures.
It is the responsibility of the person who signs the local purchase order (LPO) to verify that the
following
have been, done whether or not he/she actually collects the goods concerned.
(i) That the correct quantity has been received and signed.
(ii) That the quality and price of goods are as agreed.
(iii) That all goods delivered have been securely and inventory records appropriately updated.
(iv) That the delivery note is checked, signed, and forwarded to the financial officer to await the
invoice.
Purchases under petty cash must not exceed the maximum amount established and documented by
the financial officer.
Procurement staff and all members of the procurement committee will be required to sign a ‘conflict of
interest document stating that they will not purchase goods or services from a company they have a
vested interest.
THE PROCUREMENT PROCESS REPORT
Upon receipt of requisitions, the procurement officer will first verify that the requisition is
properly
approved according to the signing authority. He/she will then enter the requisition details into the
procurement report worksheet. After this, he/she will begin the process of sourcing the goods.
The procurement report worksheet is updated to reflect requisitions as they are received. It also
includes information on the status of each procurement requisition, complete with an expected delivery
date. This is to be submitted to the projects department on a monthly analysis.
The procurement officer is required to present a monthly financial and narrative report on procurement
to the executive director, through the administrative assistant and a copy is forwarded to the
financial
officer.
VENDOR SELECTION
Careful selection of vendors should be done to ensure that the best possible price, quality and
delivery
time available within the markets is obtained. A list of suitable vendors (the list of pre-qualified
vendors), for each type of goods and services based on letters of introduction and past performance,
shall be maintained. This will make the process of vendor identification much faster. The vendor list
shall be reviewed and updated periodically to ensure that current known factors are taken into
consideration.
Once the previous year’s list of vendors has been updated and approved by the procurement
committee, procurement of goods and services can be affected. Vendor selection for inclusion on the
list of pre-qualified vendors will take place once per year and will be done by the procurement
committee.
VENDOR SELECTION CRITERIA
The following set of criteria is essential for deciding on the choice of vendors:
(i) Price
(ii) Quality of goods/services. Such a justification must be verifiable.
(iii) Availability of goods/services within the required delivery time.
(iv) After sale services, including the availability of parts/supplies.
(v) Bidder’s previous records of performance and service.
(vi) Ability of bidder to render satisfactory service in this instance.
(vii) Financial stability of the vendor.
(viii) Availability of bidder’s representatives to call upon and consult with
(ix) Payment terms
(x) Warranty offered.
(xi) Ability to provide samples
PROCEDURE FOR TENDER
The procurement office and the heads of the various departments may recommend potential vendors
but the selection of those invited will be left to the discretion of the procurement committee. The
procurement officer will send an invitation to tender to each supplier listed to be invited. The
vendors
will pick up tender documents at Al Karrar Engineering Co offices specifying the goods and details, or
any relevant information needed to get accurate bids. All suppliers must receive the same
information.
USE OF DEALERS AND SOLE SUPPLIERS
In the interest of ensuring quality, reliability and timeliness, the procurement officer may establish
purchase agreements or contracts with main dealers of regularly purchased goods. Where possible
due to other factors, the procurement office will negotiate rates and discounts with the supplier or a
method to determine the price for invoice justification. These agreements and prices (net of
discounts)
should be reviewed annually to ensure that they are competitive.
LOCAL PURCHASE ORDERS (LPO) WITH VENDORS
The LPO is a contract with vendors that should include all information regarding the goods and
services being procured as well as standard terms of delivery, payment and arbitration in case of a
dispute. If contracts are precise and clear, the possibilities of disputes will be reduced, and Al
Karrar
Engineering Co will stand a far greater chance of receiving the goods and services as expected. Upon
selection of a vendor, a legally binding contract or work order should be drawn up for the goods and
services in question and signed by both parties prior to procurement. Detailed specifications:
quantities, unit prices, delivery deadlines, locations, and payment schedules must be specified in
such
contracts.
ORDER FOR RECURRING REQUISITION
Procurement of a recurrent nature, i.e., where the same goods and services may be issued several
times a year, one vendor may be selected for a period of up to one year. In some cases, particularly
for services, contracts for the goods or services can be drawn up once, which may then be referenced
every time those goods or services are required without requiring separate quotations and contracts
on each occasion. In other cases, particularly for regularly purchased goods, vendors can be selected
once, but separate contracts are drawn-up on each occasion the vendors are used.
CERTIFYING DELIVERY OF GOODS AND SERVICES
The procurement process cannot be completed without certification that the goods and services
procured have been received entirely to Al Karrar Engineering Company’s satisfaction, in particular,
to the satisfaction of the requisition. The procedure for receiving goods and services is therefore
important in ensuring that vendors have entirely met their obligations. Once Al Karrar Engineering Co
has certified that goods and services have been received to their satisfaction, it has little further
resources to complain about a vendor’s performance, and payment can then be made.
In all cases, the certification of receipts of goods and services is a pre-requisite to Al Karrar
Engineering
Co and the following guidelines are essential for that purpose.
(i) The procurement office should ensure that goods and services are checked against contracts,
waybills, invoices, or delivery notes.
(ii) Requisition department at the time of delivery will facilitate the receiving and checking of
goods
and services whereby the receiving person will have to sign the delivery notes or any other
documents during delivery.
(iii) Physical checking should be done by the requisitioning department and not by the procurement
office.
(iv) In some cases, receiving of goods and physical checking of goods or services may be
delegated to other [name of organization] officers who are so authorized by the procurement
officer. Such might include cases where goods or services are delivered directly to a project
field location; or where a specialist’s technical certification is required.
(v) Any differences between documents done and physical checks should be noted and reported
to the procurement officer for action.
PAYMENT-PROCESSING PROCEDURE
The recipient department is responsible for preparing payment requisition which then is forwards to
the procurement office for checking and certifying. The document is then sent to the finance
department for further checking and necessary approval and authority to pay. All payments must be
made in accordance with the contractual terms between the vendor and Al Karrar Engineering Co and
in reference to the financial policies.
2. PROCUREMENT OF SERVICES
APPOINTING AND PAYING CONSULTANTS
Consultants’ services shall be sought for:
(i) A job for which the required technical expertise does not exist in-house at Al Karrar
Engineering Co
(ii) A job that is not ongoing and hence does not require full-time staff.
(iii) A job that does not require more than 6 months of continuous engagement.
The following procedure shall be observed for engaging the services of a consultant at Al Karrar
Engineering Co.
(i) The decision to hire the services of a consultant shall be taken by the
(ii) executive director in liaison with the heads of the various departments in consultation with the
board of directors.
(iii) The executive director shall send an invitation to the specific appropriate consultant(s)
requesting for proposal for the consultancy by a stated date.
(iv) The proposals received shall be reviewed by a panel composed of the various heads of
department and the ensuing recommended name shall be submitted to the executive director
who shall discuss it with the Al Karrar Engineering Co-executive committee.
(v) The terms of reference for the consultancy shall be mutually agreed upon and the financial
officer shall be involved in the negotiation of financial aspects of the terms.
(vi) The contract agreement shall be signed by both parties before the commencement of the
consultancy assignment.
(vii) Payment is conditional on satisfactory completion of the whole job unless the agreement
provides for instalments at the completion of specifically agreed components/tasks.
APPOINTING AND PAYING TEMPORARY STAFF
Temporary staff include locum, short-term project staff engaged for on-off tasks. The following
procedure shall be observed for engaging the services of temporary staff.
(i) The temporary staff is engaged by the executive director in liaison with the department in need
of the staff and the financial officer.
(ii) The letter of engagement is issued by the executive director stating the temporary status of
the employment and the agreed terms.
(iii) A temporary staff is expected to comply with all the policies of Al Karrar Engineering Co while
in the service of Al Karrar Engineering Co
(iv) Payment shall be made at the end of the month along with the payroll of the regular
staff.
APPOINTING AND PAYING CASUAL WORKERS
Casual workers will be those engaged in project work especially manual work, for one to several days.
The following procedure shall be observed for engaging the services of casual workers:
(i) The casual workers are engaged by the heads of departments upon the approval of the
executive director.
(ii) A list of casual workers (name and identity numbers) shall be maintained by the head of the
department stating the terms of reference for the casual worker.
(iii) The letter of authority for the engagement of casual workers shall be issued by the executive
director to the head of the department, stating the terms of reference for the casual workers.
(iv) Casual workers are expected to comply with all the policies of Al Karrar Engineering Co while
at their service.
(v) Payment shall be made on a daily or weekly basis.